Westbrook Currents TL;DW! meeting summary · westbrookcurrents.com/tldw/2026-05-05-planning-board
‹ TL;DW! Planning Board

Westbrook Planning Board — May 5, 2026

Westbrook High School (Room 114), 125 Stroudwater St. (Hybrid via Zoom) · 7:00 PM

Attendance: Present: Chair Larry McWilliams, Vice Chair John Turcotte, Karen Axelson, Nancy Litrocapes, Robin Tannenbaum, Oriana Farnham (alternate). Absent: Jason Frazier, Kevin Price, Lucas Schrage (alternate).

Watch the full video on Vimeo ↗ Meeting packet ↗

Each item shows a timestamp like 57:13 (minutes:seconds) or 1:52:13 (hours:minutes:seconds). Tap it to jump to that moment in the video.

Quick read: Stroudwater Meadows housing project draws heavy traffic opposition. Three large residential projects were workshopped in one unusually packed meeting; two more items ran out of time.

This was an unusually long meeting (3.5 hours) with six scheduled items and heavy public turnout; summarization necessarily condenses and selects more than usual.

I. Roll Call

7:22
Roll Call, Minutes & Agenda Change Chair Larry McWilliams announced that the applicant for 160 Conant St. (NextGen Holdings) asked to be removed from tonight's agenda.

Chair Larry McWilliams announced that the applicant for 160 Conant St. (NextGen Holdings) asked to be removed from tonight's agenda. That item was not reviewed. On roll call, six of nine seated members were present: McWilliams, Oriana Farnham, Robin Tannenbaum, Nancy Litrocapes, Vice Chair John Turcotte, and Karen Axelson. Lucas Schrage, Kevin Price, and Jason Frazier were absent.

✓ Minutes of the April 7, 2026 meeting approved unanimously by roll call, 6–0. Moved by John Turcotte, seconded by Oriana Farnham.
9:52
Workshop — Stroudwater Meadows (24-001219) Tuck O'Brien (incoming JB Brown & Sons president), Caleb Barassa (Gorrill Palmer), and Tyler Norod (Westbrook Development Corporation) presented a…

Tuck O'Brien (incoming JB Brown & Sons president), Caleb Barassa (Gorrill Palmer), and Tyler Norod (Westbrook Development Corporation) presented a substantially revised concept. It has 322 units of mixed market-rate and income-restricted housing. That is down from an original roughly 740-unit concept shown to the board in December 2024. The units are now clustered near Stroudwater Street, per board and staff feedback.

Roughly half of Westbrook households would income-qualify for the affordable-phase units. Those units are planned as family (not senior) housing at 50–60% of area median income.

Point/Counterpoint — arterial access vs. Stroudwater Street. Most of the roughly thirteen public speakers raised traffic concerns. Many asked for direct vehicle access to the nearby arterial highway, instead of routing all project traffic onto Stroudwater Street.

“The traffic has been substantially increased... adding this development where you have 300 units... most of them will be coming down our street again.”— Fred Fowler, Westbrook St., Portland (public comment) · 31:22

“Why can't there be a pedestrian overpass like there is on Lawrence Street for kids at Rock Row to get through the schools through this development... My message to the Planning Board is please don't have vehicle access to Stroudwater Street.”— Jane Cody, resident (public comment) · 33:32

Advocates for the abutting Randall Farm spoke separately: a resident presenting concerns on behalf of owner Mr. Randall, and Maine Farm Bureau President David Kent. They asked for a permanent fence and vegetative buffer. The aim was to protect the working cattle farm from tenant complaints about normal farm noise and odors. They cited Maine's right-to-farm law.

1:02:55 City Planner Rebecca Spitella explained that the arterial is a freeway-type roadway. An at-grade (street-level) pedestrian crossing isn't permitted there under Department of Transportation standards. A grade-separated crossing (one over or under the road) was examined in an earlier design but proved too costly.

Stroudwater Street's capacity and mitigation options (ways to reduce the traffic impact) are under review, including a possible roundabout at the middle-school intersection. This review is part of the traffic movement permit process. The proposal's density and building types are already permitted under current zoning.

Vice Chair John Turcotte 1:14:59 pressed for an updated traffic study reflecting actual school traffic patterns. He also noted that the largest building sits right next to an abutting home, and asked about buffering.

Member Robin Tannenbaum asked that the biggest building not be placed up against the road. Nancy Litrocapes and Chair McWilliams later asked the same. Tannenbaum also urged a more contextual, pitched-roof architectural style.

Chair McWilliams 1:40:28 asked to see traffic projections for both the 322-unit plan and the original larger concept. He was concerned that the reduced plan is a first phase of further buildup, since roughly half the parcel remains undeveloped. Staff and the applicant confirmed no future development is currently planned there, but could not rule it out long-term.

Member Oriana Farnham 1:24:40 asked that affordable units not be clustered separately from market-rate units, for equitable amenity access.

✓ No vote — workshop item. The applicant expects to return with a formal application in summer 2026, after state Site Law and traffic-permit submissions.
1:48:34
Workshop — Bridgton Rd., Wormell Farms LLC (26-000123) Matthew Pelletier (Terradyn Consultants) presented 109 units across eleven two-and-a-half-story buildings on a ~60-acre parcel between 197 and 299…

109-Unit Multifamily — Third Phase of the Former Wormell Farm

Matthew Pelletier (Terradyn Consultants) presented 109 units across eleven two-and-a-half-story buildings on a ~60-acre parcel between 197 and 299 Bridgton Road. It is the third phase of a larger former farm property, following an existing 18-unit duplex complex and the in-progress 118-unit Brooks Edge Farm. Roughly 52 of the 60 acres, including extensive Minnow Brook wetlands, would remain permanently open space.

Neighboring residents raised concerns about a building sited only about 15 feet from a property line, light pollution, and — most substantively — longstanding road-runoff flooding tied to the 2006 state repaving of Route 302. Abutters said that repaving already funnels stormwater onto their properties. They fear this project's new curbing will worsen it. Staff acknowledged this drainage history requires follow-up research with the City Engineer.

Board members Oriana Farnham and John Turcotte raised headlight-glare concerns from parking facing directly into abutting backyards. Chair McWilliams suggested reorienting one building to reduce a sightline into a neighboring yard.

Chair McWilliams, with other members agreeing, asked whether the City could develop a cumulative, city-wide traffic framework rather than evaluating each large development in isolation. Staff noted that question falls to City Engineering/Council rather than the board's project-by-project review.

✓ No vote — workshop item.

Workshop — 547 Saco St., MTR Development LLC (26-000275)

2:47:29
72 Units, Six Buildings — New Ownership of a Former Farm Property Dustin Roma (DM Roma Consulting Engineers), representing new owner MTR Development, presented 72 units across six 12-unit buildings on a former far…

Dustin Roma (DM Roma Consulting Engineers), representing new owner MTR Development, presented 72 units across six 12-unit buildings on a former farm property. The existing farmhouse would be split onto its own lot, and a barn would be retained for storage. The buildings are proposed at two and a half stories with pitched roofs and dormers, a deliberately different style from boxier recent construction.

The project would extend the City's sidewalk network toward El Maple along Saco Street. The applicant anticipates phased construction (roughly two buildings per year). The applicant also flagged time pressure from Saco Street's scheduled repaving this year.

Neighbors raised concerns that two buildings are sited close to a property line abutting a home with a pool. They also said density, height, and parking are all at or near the zoning maximum, with no dedicated visitor parking identified. And they said the wetland delineation (the mapping of wetland boundaries) underlying the 72-unit count isn't yet finalized.

Staff clarified that site plan review (the Planning Board's review of the detailed plan for a building project) proceeds in two stages. The first is this conceptual sketch plan. The second is a detailed final application, including wetland surveys, stormwater design, and a required performance bond (a financial guarantee that the work gets done).

Staff also clarified that the zoning ordinance (a city law) sets an objective development standard that the board applies, rather than a discretionary housing-type policy choice.

Board member Robin Tannenbaum and Chair McWilliams praised the pitched-roof architectural style as more contextual than typical flat-roofed apartment buildings. Member Nancy Litrocapes asked whether straightening the site's curved driveway could pull the two buildings nearest the pool-owning neighbor's property line further back. The applicant said there appeared to be substantial room to do so.

✓ No vote — workshop item.

Items Not Reached

2:48:31
Rock Row South Campus Building SG & SR; Land Use Ordinance Height Amendment At about 9:45 PM, after two lengthy workshop items, the board decided not to take up the items scheduled after the 547 Saco St. item.

At about 9:45 PM, after two lengthy workshop items, the board decided not to take up the items scheduled after the 547 Saco St. item. These were the Rock Row South Campus Building SG & SR site plan (the 267-unit/parking-garage building previewed at the April 7, 2026 Rock Row Phase 3 master-plan workshop) and a Land Use Ordinance amendment removing the 2.5-story height limit in Residential Growth Area 2 and 3 (while retaining the existing 35-foot maximum height).

Two members said they couldn't attend the proposed May 19 makeup date. Staff said May 19 was preferred for Rock Row. Staff would check for a quorum (the minimum number of members needed to vote), with June 2 as the fallback. Rock Row was heard on May 19; rescheduling of the height amendment wasn't discussed.

✓ Deferred — no discussion held.
Not a replacement for watching — and not an official record. This summary highlights the meeting's key discussions and decisions; it's not a substitute for watching the full meeting, and summarization necessarily condenses and selects. It's also an unofficial product of Westbrook Currents, an independent site — not the City of Westbrook — and may contain mistakes. For complete context or the official record, watch the full video or see the City's approved minutes.

How this was made: Produced from the meeting video (linked above, hosted on the City's Vimeo showcase). The audio was transcribed with AI-assisted speech-to-text and speaker identification. This process cross-checked names against the official Planning Board roster, attributed speakers from context (introductions, roll-call order, direct address by the Chair) rather than the raw diarization labels alone, and drafted this summary and the quoted excerpts. Quotes are lightly cleaned of filler words/false starts but not reworded. Reviewed by Gerald Doyon.